Work to begin this week on second phase of Wilmot Recreation Complex
Doug Coxson
Published on
Jun 22, 2010
Check out photos and plans of Phase 2 at our blog.
Shovels are expected to hit the dirt at the Wilmot
Recreation Complex this week after Wilmot council bit the bullet in a decision
to green light the long-awaited build for Phase 2, even after contractor bid
prices came in higher than expected.
Coming in at 3.9 per cent above a February budget estimate
that included a $1.1 million list of enhancements, the project to build an
eight-lane, 25-metre competitive swimming pool, leisure pool, walking track and
senior and youth centres will now cost taxpayers $11.6 million.
Initially budgeted at $9.8 million back in May 2009, the
cost jumped in recent months as enhancements were added to match stakeholder
and community input.
Two major enhancements include a second elevator and wider
building footprint to accommodate a wider walking track and wider aisles in the
pool’s spectator gallery.
A $160,000 dehumidifier is expected to eliminate chlorine
odours in the pool area. Enhanced mechanical and electrical equipment, pool
plumbing and design layout, including timber roofing will cost an additional
$160,000.
Other enhancements include plastic lockers in the change
rooms and track area, acoustical panels for the pool and seating around the
pool deck.
Inflationary costs, a hot construction market and the
harmonized sales tax are all playing into the higher bid prices for the
project.
Councillors were advised in March of a predicted increase in
material costs that could push the final tally even higher Tenders closed May
11, giving members of the project team, including township staff, G.B.
Architect and Jackson-Barill Management Inc., a month to review bids to ensure
they qualified. All of the tenders accepted for the project are from the lowest
qualified bidder.
Guy Bellehumeur, of GB Architect Inc., provided council with
an outline of reasons why the bids came in at significantly more than cost
estimates delivered in February, not the least of which is the amount of
federal and provincial infrastructure money flowing into the construction
industry.
Bellehumeur said the influx of money means contractors can
essentially “cherry pick” the jobs they want while demanding higher fees to do
the work.
Bellehumeur said many private-sector projects across the province
have closed at more than six per cent higher than initial budget estimates,
with some municipalities seeing skyrocketing construction fees.
“Other major pool projects are coming in at eight per cent
and 25 per cent over budget,” he said, cautioning council against delaying
Phase 2. “We’ll soon be experiencing bids from low quality bidders and trades
because all the good ones are busy.
“This project is shovel ready.”
Councillors were offered the alternative options of delaying
construction in hopes of getting better bid prices, or slashing the list of
enhancements to cut costs.
Bellehumeur urged council to not to entertain the
alternatives since most enhancements cannot be added later and there’s no
guarantee bid prices will come down.
“We sincerely doubt better pricing would be achieved,”
Bellehumeur said.
“This has come to the table after a lot of hard work from
members of staff and project team,” commented Mayor Wayne Roth, advising
council against considering any option that would delay the project, or reduce
the number of added features. “The list of enhancements grew, but I’m very
pleased with this list of additions because it makes our pool that much better.
If you take these things out, most of them can never be added.”
“I really see the enhancements as an evolution of the whole
design anyway,” commented councillor Elliot Fung. “I don’t see any reason why
we shouldn’t g with Option A. This meets the needs and desires of the people of
the township.”
Councillor Les Armstrong agreed. “I’m glad to see we’re
ready to go because I think many people are waiting to see this project move
ahead.”
Referring to delays that plagued the opening of the twin ice
pads in Phase 1, councillor Terry Broda confirmed a timeline of 60 weeks for
the project, including time to test the facility’s equipment and ensure the
pool’s water quality.
“There are so many things that can go wrong in any project —
weather, strikes... We hope for the best and aim for 60 weeks,” Bellehumeur
said.
“What steps have we taken to ensure people who have
registered for the fall swim programs will be swimming in the new pool?,” Broda
asked. “I fear 800 children signing up in the summer and the pool isn’t ready
until October.”
Facilities and recreation director Scott Nancekivell said
the old pool will remain open until the new facility is ready to accept
programs.
“We do have a backup plan,” said Bellehumeur. “We can’t
control what happens, but we can control what we do to make sure it doesn’t
happen. The manpower and time allotted to make this work the best we can is
there.”
Council will receive monthly updates throughout the build
and staff will be on site every two weeks to track its progress.
The project is being financed largely through a $6 million
grant from the federal and provincial governments’ Building Canada Fund.
Fees collected by the township from new building
developments will cover about $1 million of the final cost, while $4.6 million
will come from township reserve funds.
“This whole complex, in terms of its utilitarian usage, is
going to be a great place for young old and everyone in between,” mayor Roth
said, thanking staff and the project team for working well together throughout
the planning stages.
“This is a great moment for Wilmot moving forward. We’re
going to have a recreation complex that’s going to be the envy of many in the
province of Ontario. And it’s been developed at a reasonably low cost compared
to others going up.”
“A similar project I’m aware of is running from $11 million
to $23 million.”
News of council’s decision to move ahead with the project
spread quickly last week.
“We’re all pretty excited,” said Wilmot Aquatic ACES head
coach Joni Maerten-Sanders. “Now we can start hosting meets, which will bring
in a huge economic impact to the town.”
For years the swim club has struggled to host other swim
teams because of a lack of deck space at the community pool. With 75 swimmers
and 25 master swimmers sharing only 10 hours of pool time a week, training for
meets was difficult.
“We’re swimming with close to 10 kids in a lane,” said
Maerten-Sanders. “It puts stress on the kids to train properly.”
The additional lanes at the new aquatic centre will resolve
the issue and allow the club to expand.
Rumours of the pool tenders coming in over budget had
Maerten- Sanders a little worried construction might be delayed, but she was
hopeful council would make the right decision.
“New Hamburg is lucky to have a facility to begin with,” she
said, adding the club gets calls from parents in south and west Kitchener
looking to join because of a lack of competitive swim clubs in the cities.
She’s hopeful the new Wilmot pool will attract swimmers from
a wider geographic area.
On-site work is expected to begin immediately, with an
opening date planned for August 2011.